|
Page 2 |
|
|
|
| The concrete footers for the back portion of the boathouse were installed onto the bedrock. |
![]()
|
![]()
|
![]() |
![]() |
| Columns to
support the stairway were placed on the concrete footer, and
steel rebar, plates, and I-beams were installed on them.
|
![]()
|
Due to a modification in the
plans, a portion of the previously concrete-sprayed wall
needed to be re-exposed and then be drilled for the
installation of rebar to reinforce the back concrete wall of
the first floor of the boathouse.
Constructing the forms for the back wall.
|
![]()
|
![]()
|
| An existing access road
needed additional protection to allow for the movement of
large equipment to the top of the cliff.
|
| The owner has an antique wooden boat to be stored in this boathouse. We needed to design a custom lift for this boat. This lift was made by Hi-Tide |
![]()
|
![]()
|
The superstructure of this boathouse is being completed by others.
When the job is finished, we will post photos.
|
To see the progression of this job, click on an image to see an enlarged view At the beginning of the job, a long-stick excavator fitted with a support frame was used to lower our 331 Bobcat excavator to the bottom of the cliff. The bobcat was used to dredge an area on the lakebed to prepare it for the construction of the foundation for the boathouse. A steel I-beam frame was constructed to enable the bobcat to reach the area to be dredged. A silt curtain was installed to prevent turbidity from entering the lake. The spoil was then brought to the top of the cliff using the long-stick excavator, loaded onto a dump truck, and transported to a spoil disposal area. |
|
Click on an image to
see an enlarged view
As in the previous job, holes were drilled into the cliff face for steel rock anchors to be grouted in place. Wire mesh was welded to these anchors in preparation for sprayed concrete to be applied to stabilize the cliff face. |
A steel sheet pile seawall with support poles drilled and grouted into bedrock was installed. We reshaped the cliff face to prepare for the drilling of rock anchors and the application of sprayed concrete to stabilize the bank. The job we had previously completed is visible in the photograph with the red border. (For more pictures of this completed job, visit the Completed Projects page). Steel I-beams and framing were installed to support a wood wall of 6" x 6" timbers against the foot of the cliff. |
![]() |
Concrete was sprayed onto the wire mesh and the cliff face. This stabilizes the face and prevents further erosion. This is the same method we used in the previous job (see Completed Projects page). After the final application, the cliff is now stabilized, has a natural appearance, and blends well with the property next door. |
|
We then went back to installing the
piers to support the boathouse.
Click on an image to see an enlarged view |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
|
All six piers are now installed, and the installation of the steel sheet pile wall along the shoreline is complete. |
![]() |
![]() |
![]() |
![]() |
|
The temperatures at the job site were rather chilly this spring. One morning we were greeted with a thick coating of ice over everything. Click on an image to see an enlarged view |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
|
|
The nine piers are now completed. Steel square tube was installed on the piers, and is used for support columns for the entire structure. Steel I-beams were brought down and placed on the support columns. They were then bolted and welded in place. |
![]() |
|
We have used our new modular aluminum barge to help place the steel during this phase of construction. |
|
All of the steel supports for the
boathouse are now in place. The concrete pad at the top of the cliff where the long-stick excavator sat was topped off with a timber wall. |
![]() |
![]() |
| The wall was then backfilled, and will be covered with rolled sod for a finished lawn. |
![]() |
![]() |
We replaced cedar trees which had been removed along the property boundary. |
|
[ Home ] [ Seawalls ] [ Docks and Decks ] [ Launch Ramps ] [ Boatlifts ] [ Pile Driving ] [ Dredging ] [ Current Worksite ] |